Construction Projects
Parking Structure
Estimated Cost: $28 million
Project Timeline - 9/6/07 - 5/1/10
Design/Build Award & Contract - 5/21/08 - 7/17/08
Preliminary Design & Construction Documents - 5/13/08 - 10/30/08
Construction - 3/11/09 - 5/1/10
Project Completed!!!
Craven View Drive Extension Project - Adjacent to Parking Structure 1 and Parking Lot N
Project Completed
Craven View Drive & Campus Way Traffic Signal Project
Estimated Cost: $225,000
Schematic Design Phase - completed
Bidding - 10/27/09 - 11/17/09
Contract Award - 11/23/09
Construction Phase 2/15/10 - 06/02/10
Project Completed
Public Safety Building
Estimated Cost: $7.5 million
Schematic Design Phase - Completed
Preliminary Design Phase - Completed
Bidding - Completed
Construction Phase 1/5/10 - 2/24/11