Construction Projects


Parking Structure
Estimated Cost: $28 million

Project Timeline - 9/6/07 - 5/1/10
Design/Build Award & Contract - 5/21/08 - 7/17/08
Preliminary Design & Construction Documents - 5/13/08 - 10/30/08
Construction - 3/11/09 - 5/1/10
 
Project Completed!!!

Craven View Drive Extension Project  - Adjacent to Parking Structure 1 and Parking Lot N

Project Completed


Craven View Drive  & Campus Way Traffic Signal Project 


Estimated Cost: $225,000
Schematic Design Phase - completed
Bidding - 10/27/09 - 11/17/09
Contract Award - 11/23/09
Construction Phase 2/15/10 - 06/02/10

Project Completed


Public Safety Building
Estimated Cost: $7.5 million

Schematic Design Phase - Completed
Preliminary Design Phase - Completed
Bidding - Completed
Construction Phase 1/5/10 - 2/24/11