Humanities Building

 

This project will design and construct a 52,400 ASF/83,544 GSF building to support 1,930 FTE. The building will provide lecture classrooms, graduate research space, discipline specific centers, faculty offices, administrative support space, and conference rooms for the Humanities programs and other supporting disciplines on campus.

Funding:

TBD

 

Total Project Cost:

$54,900,284

 

Construction Cost:

$45,747,553

 

Project Manager:

Diane Malone

(760) 750-4658

dmalone@csusm.edu

Architect:

TBD

 

Contractor:

TBD

 

Current Status:

Feasibility Study

(Not funded in 09/10 Capital Program)

 

Schedule:

TBD

Last Updated:

March 05, 2008

 

Office of Planning, Design and Construction

Craven Hall 5111

333 So. Twin Oaks Valley Rd.

San Marcos, CA 92096-0001

 
"Becoming nationally recognized leaders in higher ed administration"
 

PDC Home | CSUSM Home | CSUSM Search | Help for this Site | Last Revised: 03/05/2008