The proposed
project, which is the first phase of a master planned complex of buildings,
courtyards and patios provides meeting accommodations and dining opportunities
for campus and community members. The 3,238 square feet main building
includes a great room for meeting and dining, a commercial kitchen, foyer, and
support areas. The compex will also include a 600 sf covered patio, a 600
sf Library, a 416 sf Retreat Room and 500 sf Tower Room for University
gatherings. The project will be financed by gift funds.
|
Funding:
Donor Funds
Total Project Cost:
$4,853,000
Construction Cost:
$3,694,600
Project Manager:
Diane Malone, AIA,
LEED, AP
(760) 750-4658
dmalone@csusm.edu |
Architect:
Rob
Wellington Quigley, FAIA
(www.robquigley.com)
Contractor:
Grading & Utilities: L.B.
Civil
Building Construction:
Dalke & Sons
Current Status:
Construction
Schedule:
Grading & Utilities
Complete: February 19, 2008
Building Construction
Start: May 1, 2008
Occupancy: March
2009
|
Last Updated:
June 12, 2008