This project will
build a 106,509 square foot (67,438 ASF) classroom/office building that will
house the Social and Behavioral Sciences programs. The building will provide
739 seats with
461 FTE in Lecture, 51 FTE in Lower Division Lab, 132 FTE in Upper Division Lab,
Graduate Research Space, 125 Faculty Offices, Dean’s Suite, 10 Department
Suites, Support Spaces, Conference Rooms, and 2 centers. The programs that will be housed in
the SBSB are: Psychology, Sociology,
Communication/Mass Media, Economics, Political Science, Anthropology, Liberal Studies,
and Human Development.
|
Funding:
Major Capital
2006-2007
Total Project Cost:
$56,842,000
Construction Cost Estimate:
$43,132,000
Sitework
Cost:
$2,250,000
Project Manager:
Diane Malone, AIA,
LEED, AP
(760) 750-4658
dmalone@csusm.edu |
Architect:
AC Martin Partners
(www.acmartin.com)
Contractor:
Sitework: TBD
Building
Construction: TBD
Current Status:
Sitework: Bidding
Building
Construction: Construction Documents
Schedule:
Sitework - Start:
July 2008
Sitework -
Completion: November 2008
Building Construction
- Out to Bid: October 2008
Building
Construction - Bid Date: November 2008
Building Construction
- Start: December 2008
Building Construction
- Completion: August 2010
Occupancy: January
2011
|