Parking Lot F
Project completed in August 2006
The project has provided 1,555 parking spaces, 355 more than anticipated when the RFP was developed.
Site grading began in May 2006
Paving began in June 2006
Striping and Light Pole preparation continued throughout July
Students began using Parking Lot F in August 2006 on the first day of school.