Project Start Date: Wed 7/3/02
Project Finish Date: Fri 10/4/02
Resources and Assignments | Start | Finish | Work |
|---|---|---|---|
Unassigned | Mon 8/5/02 | Fri 10/4/02 | 0 hrs |
Review all current business process to ensure PS will meet or exceed requirements | Mon 8/5/02 | Fri 8/16/02 | 0 hrs |
IITS to review conversion documents | Mon 8/12/02 | Fri 9/6/02 | 0 hrs |
IITS to run selected "test loads" | Mon 8/12/02 | Fri 9/6/02 | 0 hrs |
Benefit Program Table | Mon 8/12/02 | Fri 9/6/02 | 0 hrs |
Benefit Plan Table | Mon 8/12/02 | Fri 9/6/02 | 0 hrs |
Provider/Vendor Table | Mon 8/12/02 | Fri 9/6/02 | 0 hrs |
Coverage Codes | Mon 8/12/02 | Fri 9/6/02 | 0 hrs |
Health Plan Table | Mon 8/12/02 | Fri 9/6/02 | 0 hrs |
Leave Plan Table | Mon 8/12/02 | Fri 9/6/02 | 0 hrs |
Non Discrimination Table | Mon 8/12/02 | Fri 9/6/02 | 0 hrs |
CSU Custom Tables (3 including Savings) | Mon 8/12/02 | Fri 9/6/02 | 0 hrs |
Retirement Plan Table | Mon 8/12/02 | Fri 9/6/02 | 0 hrs |
FSA Benefit Table/Run Tbl/Form Tbl | Mon 8/12/02 | Fri 9/6/02 | 0 hrs |
COBRA Administrator | Mon 8/12/02 | Fri 9/6/02 | 0 hrs |
Coverage Group Tables | Mon 8/12/02 | Fri 9/6/02 | 0 hrs |
Life & ADD Plan Table | Mon 8/12/02 | Fri 9/6/02 | 0 hrs |
Disability/Leave Policies | Mon 8/12/02 | Fri 9/6/02 | 0 hrs |
Disability Plan Table | Mon 8/12/02 | Fri 9/6/02 | 0 hrs |
FMLA requirements are met | Mon 8/12/02 | Fri 9/6/02 | 0 hrs |
CSU Leave Acctg Time (Reporting Code Table) | Mon 8/12/02 | Fri 9/6/02 | 0 hrs |
Develop Test/Train review | Mon 8/12/02 | Fri 9/6/02 | 0 hrs |
CSU Benefit Agency | Mon 9/2/02 | Fri 9/13/02 | 0 hrs |
Checklists (evaluate type and number required | Mon 9/2/02 | Fri 9/13/02 | 0 hrs |
Develop Required Checklists | Mon 9/2/02 | Fri 9/13/02 | 0 hrs |
CSU Benefit Report Table | Mon 9/2/02 | Fri 9/13/02 | 0 hrs |
Evalue all reporting requirements for HREO | Mon 9/2/02 | Fri 9/13/02 | 0 hrs |
Develop gap queries | Mon 9/2/02 | Fri 9/13/02 | 0 hrs |
Complete needs assessment | Mon 9/9/02 | Fri 9/20/02 | 0 hrs |
Develop training sessions to meet staff requirements | Mon 9/9/02 | Fri 9/20/02 | 0 hrs |
Develop competency checklist | Mon 9/9/02 | Fri 9/20/02 | 0 hrs |
Evaluate current PERS reporting/database | Mon 9/23/02 | Mon 9/30/02 | 0 hrs |
Obtain ACES certification | Mon 9/23/02 | Mon 9/30/02 | 0 hrs |
Upload all current employee data to PS | Mon 9/23/02 | Mon 9/30/02 | 0 hrs |
Audit/Validate all PS information | Mon 9/23/02 | Mon 9/30/02 | 0 hrs |
Begin inputting of all new employee information and/or changes to current benefit data | Tue 10/1/02 | Fri 10/4/02 | 0 hrs |