Public Works/Maintenance
Total Cost |
Maintenance Services ITEMS REQUIRED TO BE SUBMITTED WITH REQUEST |
Public Works ITEMS REQUIRED TO BE SUBMITTED WITH REQUEST |
Purchase/Solicitation Type | Anticipated Time to Completion |
---|---|---|---|---|
Less than $1,000 |
|
|
JOC or Other | Up to 2 weeks |
$1,000-$49,999 Prevailing Wage Required |
|
|
JOC or Other |
JOC - Up to 2 weeks Other - 3-5 weeks |
$50,000 - $99,999 |
|
|
JOC or Informal |
JOC -Up to 2 weeks Informal - 6-12 weeks |
Over $100,000 |
|
|
Minor Cap Formal Bid | 8-15 Weeks |
Over $929,000 |
|
|
Major Cap Formal Bid | 12-16 Weeks |