Construction

  • When will construction start?

    Construction is set to kick off on December 19, 2023. Here's a breakdown of the timeline:

    -December 19, 2023: Construction fencing will be set up.

    -January 2024: Salvage operations, site studies, and hard demolition will commence.

    -January 2024 to May 2024: Initial construction phase begins with a focus on infrastructure and site improvements.

    -July 2024: Above ground construction begins.

    -July 2026: Construction is expected to be complete.

  • When will the project be complete?
    Fall 2026. Construction is expected to last approximately 2.5 years.
  • When will the new building open to students?
    This new building is expected to open in Fall 2026.
  • When will Parking Lot O close?
    Parking Lot O will close Saturday, December 16, 2023.
  • How will the university mitigate construction noise?
    To mitigate construction noise, we have scheduled construction activities during normal business hours (Monday - Friday, 7 a.m. to 4:45 p.m.), and night work is not currently anticipated. Additionally, our construction teams will adhere to noise reduction practices and regulations to minimize potential disruptions to the campus community.
  • How will traffic be impacted during construction?
    The development of the new facility will impact Campus Way, Campus View Drive and the access road to Parking Lot O. Expect traffic and delays on Campus Way and Campus View Drive due to infrastructure and utility routing. During business hours, a portion of the westbound right lane on Campus View Drive will be closed for a crane hoisting lane. Access to Parking Lot O will be temporarily closed for the campus community. Entry and exit to PS1 will be changed to right turn only off/onto Campus View Drive.
  • How is this project being funded?
    This project is partially funded by nearly $91 million in funding from the State of California.
  • How will I access the UVA during construction?
    During the initial phase of infrastructure and site improvements, access to UVA will be available through the pedestrian gate near Building D. Approximately six weeks after the start of construction, there will be a new sidewalk from Campus Way to Building B.
  • What is the ADA access during construction?
    We are actively researching the best options to maintain ADA access during construction. We will ensure that ADA access is provided. The safety and accessibility of all campus members remain a top priority.
  • Is there a quiet place to study during construction?
    Housing and Residential Life staff is in the process of identifying some quiet study locations and will post them in the UVA and website before the start of the spring semester.
  • How will we move in and out of the UVA?
    The Housing and Residential Life team are developing a plan for the end of the academic year and the 24-25 academic year. More information will be shared in the spring semester as we are closer to move-out. If you are moving out, prior to that date residents should make arrangements with housing.